©Shutter B – stock.adobe.com
Case Study
Optimization of the czech production site of a high-performance ceramics group
Project Management Consulting in Czech Republic
Company Deatils
- Supplier and manufacturer of technical ceramics with approx. 3,500 employees worldwide at 19 production sites in Europe, the USA and Asia
- Independent production site in CZ with 300 employees
Situation and Challenge
- Stabilization of the plant in CZ after short-term separation from the local managing director
- Adaptation of processes and personnel for extreme growth situation
- Creation of transparency for the German management holding company
- Introduction of corporate standards
- Labour shortage
- Eliminate uncertainty in the management team and build trust
Objective and Tasks
- Ensuring the functioning of the plant; Solution of strategic personnel vacancies / personnel expansion in production / evaluation of managers and identification of personnel changes
- Improvement of internal communication and team building in the management team
Measures and Procedures
- Building trust in local management, improving work discipline and local corporate culture
- Realization of “quick wins”, prioritization and consistent processing
- Creating transparency; Open, situational leadership style
Results and Achievements
- Hiring of specialists and executives (production, procurement, lean management)
- Revenue growth + 20% (YTD) vs. budget
- 15% increase in staff
These articles might also interest you:
Case Study
Interim COO realigns global operations footprint
A global adhesives and coatings producer with aging asset base, an imbalanced footprint with strong European bias and no digital strategy. An interim COO designed a global operations and digital roadmap, modernised plants and reshaped logistics, delivering record cost savings and a far more …
Study
Restructuring and transformation 2026
The Atreus Restructuring Barometer 2026 shows how the German economy is shifting into a structural crisis mode, which industries are particularly affected, and which levers transformation opens up.
Case Study
Turnaround of an ERP standard software implementation in aftersales
A leading intralogistics provider faced an overrun ERP project in aftersales with a threatened go-live. Through complete re-planning, clear roles, robust project management and replacement of the integrator, the programme was stabilised, IT assumed ownership and licence spend was reduced.