Case Study

Project Manager Construction Technology

230781

At leading electricity grid operator in Europe

An Atreus interim manager is supporting a major project for the construction of a high-voltage direct current transmission line at a leading power grid operator in Europe as a specialist project manager in the field of construction technology. In doing so, he is responsible for the preparation, coordination and monitoring of the technical specifications for construction execution and achieved, among other things, an improvement in communication and coordination between the specialist project managers and the asset managers.

q

Company

  • One of the leading electricity grid operators in Europe, with a focus on the expansion of renewable energies
  • More than 10,000 km of network length, coverage of several federal states and metropolitan regions
p

Challenge

  • High construction costs and ambitious completion dates
  • Lengthy approval processes
  • Different geological conditions complicate the laying of cables
  • High conflicts of interest and resistance from residents, farmers and communities
m

Goals

  • Preparation, coordination and monitoring of the technical specifications for construction execution
  • Professional assessment of the processes from a scheduling and cost-related point of view
  • Preparation for Contract / Claim Management
n

Measures

  • Review and approval of execution plans and documents
  • High regard for proper logging and documentation
  • Improve communication and coordination between specialist project managers and asset managers, with a focus on balancing technical detail and progress in the construction process
  • Presence on the construction site
x

Results

  • Clearance of all execution plans
  • Regular clarification of problematic construction situations
  • Completion of the construction phase
  • Final documentation of construction technology
  • Management and implementation of the inspection group construction in the course of the acceptance committee