Case Study

Implementation of a forward-looking project management

240047

At a leading power grid operator in Europe

A leading European power system operator faced significant challenges: ensuring security of supply for over 18 million people, and modernising and expanding the existing power grid. A detailed analysis, optimisation of the schedule and development of the execution plan were introduced as measures. Successes included the implementation of project management in accordance with valid industry standards, internal acceleration with cable suppliers and an improvement of the project plan.

q

Company

  • One of the leading electricity grid operators in Europe, with a focus on the expansion of renewable energies
  • More than 10,000 km of network length, coverage of several federal states and metropolitan regions
p

Challenge

  • Security of supply for over 18 million people, currently employing approx. 2,000 people
  • Target by 2032: Secure integration of 100% renewable energy into the grid
  • Implementation of large-scale infrastructure projects to modernize and expand the power grid
m

Goals

  • Advisory support for project management
  • Preparation of work instructions, guidelines and a resolution plan
  • Project management for the pipelines/civil engineering project
n

Measures

  • Detailed analysis, optimization and presentation of the time schedule, which includes over 3,000 activities
  • Preparation and discussion of communication instructions as well as the meeting culture in cooperation with the division manager, the program manager and the responsible PMO
x

Results​

  • Implementation of project management in accordance with applicable industry standards
  • Internal acceleration with cable suppliers and construction management
  • Improving the project plan through a successful cold-eye review
  • Approval of communication instructions and the meeting culture by the PMO and the division manager
atreus_widget managementueberlassung

Management leasing: goodbye to bogus self-employment.

Atreus’ management leasing contract model offers full legal security and flexibility for clients and interim managers.

These articles might also interest you: